  1. SYDEL dispatch system for ZDM ?Huta Katowice? foundry , (telemechanics DETEC, UTJ, SAD). Realized in 1990, in cooperation with Silesian University of Technology, Gliwice.

  2. SYDEL dispatch system for ?Elektrownia Miechowice? power plant, QKD concentrators (Elbit Gliwice). Realized in 1991, in cooperation with Silesian University of Technology.

  3. SYDEL dispatch system for ?Elektrownia Jaworzno II? power plant (OMRON controllers, Japan). Realized in 1992, in cooperation with Silesian University of Technology and Energoprojekt Katowice.

  4. SYDEL dispatch system and registering of events in blocks system for EC Kraków S.A. combined heat and power plant, QKD concentrators. Realized n in 1992, in cooperation with Silesian University of Technology.

  5. Fluidized-bed furnace supervision system for ?Elektrownia Jaworzno II" power plant, OMRON controller. Realized in 1993, in cooperation with Energoprojekt Katowice.

  6. Control and dispatch system for for turbine ABB 17 MW with heating set for EC KWK ?Chwa³owice? coal mine, B&R controller (Bernecker&Rainer, Austria). Realized in 1993 in cooperation with Silesian University of Technology, Energetyka Knurów.

  7. SYDEL dispatch system with energy balances and power control for ZK ?Przyja¼ñ? Coke works. QKD concentrators. Realized in 1993 in cooperation with Silesian University of Technology.

  8. Dispatcher database for CDE ?Elektrownia Opole? power plant (2 installations). Realized in 1993 in cooperation with Energoprojekt Gliwice.

  9. SYDEL dispatch system with energy balances for KWK ?Budryk? S.A. coal mine, QKD concentrators. Realized in 1994 in cooperation with Silesian University of Technology.

  10. Control system for shaft heaters in KWK ?Budryk? coal mine, B&R controller. Realized in 1995.

  11. SYDEL system modernization and functions extension for EC Kraków S.A., Jaworzno II power plant, EC Miechowice. Realized in 1994/1995.

  12. Dispatch and control system for auxiliary switchboard for Elektrownia £aziska S.A. power plant, CEGELEC controllers (CEGELEC, France). Realized in 1994/1995, extended in 1997 in cooperation with Elektrobudowa ZBIR Miko³ów.

  13. Dispatch, monitoring and balancing system for energy in SYDEL electro-energetic system for ?Jaworzno III? power plant, CEGELEC and FANUC controllers (FANUC, General Electric), launched stages 1-4. Realized was completed in 1997, in cooperation with Elektrobudowa ZBIR Miko³ów.

  14. SYDEL monitoring system for electro-energetic system, power control and energy balancing for ZM BUMAR £abêdy, QKD controllers. Realized in 1997.

  15. SYDEL power dispatch, control and energy balancing system for Huta Katowice S.A. foundry, B&R controllers. Realized in 1998.

  16. SYDEL electric media consumption monitoring, balancing and control system of for FIAT Auto-Poland, Tychy, (stages 1-4), QKD controllers. Staged implementation completed in 1998.

  17. SYDEL control, monitoring and energy balancing system for electro-energetic system in ?Jaworzno II? power plant, CEGELEC controllers. Stages 1 and 2 launched in 1998, in cooperation with Elektrobudowa Miko³ów.

  18. Control and visualization system for heat exchangers station in EC Chorzów, GE FANUC controller, Windows NT environment, Intellution FIX software. Realized in 1998 in cooperation with Energoprojekt Gliwice, AB-Mikro Gliwice.

  19. Control and visualization system for Grodków wastewater treatment plant, B&R controller, Intellution FIX software. Realized in 1997/1998.

  20. System for proces control in Szamotu³y wastewater treatment plant, B&R controller. Realized in 1998.

  21. SYDEL system for Elektrownia Jaworzno III S.A., power plant III, stage 4 dedicated to power and energy balancing and reporting. Realized in 1999.

  22. SYDEL system for Elektrownia Jaworzno III S.A., power plant II dedicated to control and monitoring of general auxiliary switchboard and direct current switchboard (stage 3). Realized in 1999.

  23. SYDEL system for FIAT Auto-Poland, Tychy, stage 5 dedicated to balances, reports and monitoring of heat energy of non-electrical media. Realized in 1998.

  24. SYDEL system for KWK Budryk S.A. coal mine, stage 2 dedicated to monitoring, balances and reports on electric energy, additionally interventional control of exhausting machine. Realized in 1998/1999.

  25. SYDEL control, monitoring and energy balancing system for Huta Zawiercie S.A. foundry, MODICON Premium controllers. Realized in 1998 in cooperation with Elektrobudowa ZBiR Miko³ów.

  26. SYDEL control, monitoring and energy balancing system for ZEW Racibórz S.A., MODICON Premium controllers. Realized in 1998 in cooperation with Elektrobudowa ZBiR Miko³ów.

  27. Dispatch and visualization system for generators and 110/220 kV stations. Elektrownia Halemba power plant, Ex MST and Ex Mini controllers (Elkomtech £ód¼), Intellution FIX utility software. Realized in 1998 in cooperation with AB Micro Gliwice.

  28. SYDEL system for monitoring, registering, control and electro-energetic system energy balancing (surface and underground switching stations )for KWK ?Czeczott? coal mine, QKD and B&R controllers. Realized in 1999.

  29. SYDEL system for monitoring, registering, control and electro-energetic system energy balancing (surface and underground switching stations) for KWK ?Piast? coal mine, QKD and B&R controllers. Realized in 1999.

  30. SYDEL system for monitoring, registering, control and electro-energetic system energy balancing (surface and underground switching stations )for KWK ?Ziemowit? coal mine, QKD and B&R controllers. Realized in 1999.

  31. Integration of SYDEL systems for ?Piast?, ?Ziemowit? and ?Czeczott? coal mines in the domain of electric energy consumption control. Realized in 2000.

  32. SYDEL monitoring, registering, control and energy balancing system for Góra¿d¿e Cement S.A., B&R controllers, SEPAM digital protection, Landis & Gyr metering system (Siemens). Realized in 1999 and 2000 (in stages).

  33. SYDEL control, monitoring and energy balancing system for general utility switch-boards in Elektrownia £aziska S.A. power plant, Modicon Premium controllers. Realized in 1999/2000 in cooperation with Elektrobudowa ZBiR Miko³ów.

  34. Second SYDEL control, monitoring and energy balancing system for Huta Zawiercie foundry, Modicon Premium controllers. Realized in 2000 in cooperation with Elektrobudowa ZBiR Miko³ów.

  35. Visualization and control system for wastewater plant in Elektrownia Jaworzno II power plant, Simatic controllers, SCADA WinCC system. Realized in 2000.

  36. SYDEL control, monitoring and energy balancing system number 2 development in Huta Zawiercie foundry, Modicon Premium controllers. Realized in 2000.

  37. Visualization system for Kosorowice wastewater plant. Bernecker & Rainer controller, ASIX utility software. Realized in 2000.

  38. Modernization of instrumentation and automated control systems as well as electrical system for grit separator for Zabrze ¦ródmie¶cie wastewater plant. TSX Schneider controller, Monitor 77 utility software (Schneider). Realized in 2000.

  39. Comprehensive modernization of SYDEL v. 5.0 monitoring and energy balancing system in Zak³ady Koksownicze ?Przyja¼ñ? S.A. coke works, QKD controllers. Realized in 2001-2003.

  40. Realization of SEPAM 2000 digital protection concentrators (128 items) and integration of them with SYDEL system, development of SYDEL system in Góra¿d¿e Cement S.A. with additional switching stations. Completed in 2001.

  41. Development of SYDEL system in FIAT Auto-Poland SA in Tychy with SEPAM 2000 protection, and PM 600 metering systems and inclusion of new switching stations to the system. Realized in 2001 in cooperation with Schneider, Poland.

  42. Control, regulation, visualization and registering system for heat exchanger unit in Megawat Knurów, B&R controller, SCADA Asix system. Realized in 2001.

  43. Control, regulation, visualization and registering system for heat turbine for Megawat Knurów, B&R controller, SCADA Axis system. Realized in 2001

  44. System for monitoring of electro-energy system and energy balances in Centrum Handlowe Targówek shopping mall (CHT2 Carrefour) in Warsaw, B&R controller, SCADA FIX Intellution system. Realized in 2001.

  45. SYLOC system for comprehensive company management (ERP works logistic)for Sicherung Dienst Staemmler, Monsheim, Germany. Realized in 2002-2004.

  46. System for comprehensive company management (ERP works logistic)for BahnDienste BDS Monsheim, Germany. Realized in 2002-2004.

  47. System kompleksowego zarz±dzania firm± (ERP) SYLOC LPS, Monsheim Niemcy, realizacja: 2002-2004.

  48. Dispatch and control system for installation of steam in 120 MW turbine stuffing boxes, Marica power plant, Bulgaria, PowerPanel B&R controllers. Realized in 2002.

  49. System for control and visualizing for 110/6 kV electro-energetic station, Modicon Premium controllers, SYDEL v. 5 system, for ELSEW (Zawiercie foundry). Realized in 2002 in cooperation with Elektrobudowa S.A.

  50. System for visualizing, registering and energy balancing of electro-energetic system for Megawat Knurów, ELBIT controller, SYDEL v. 5 system. Realized in 2002.

  51. Modernization of balancing module of SYDEL system (version 5, module ?Energy?) in Huta Katowice foundry (PHS S.A.). Realized in 2003.

  52. Comprehensive modernization of SYDEL v. 5 system for monitoring and energy balancing in Elektrownia Jaworzno II (PKE S.A.) power plant. Realized in 2002-2003.

  53. Comprehensive modernization of SYDEL v. 5 system for control ABB 17 MW turbine in EC Chwa³owice (Kompania Wêglowa) heat and power plant. B&R controllers. Realized in 2003.

  54. Visualization and control system in Oczyszczalnia ¦cieków ?Zgorzelec? wastewater plant in Jêdrzychowice. B&R controllers, SYDEL v. 5 system. Realized in 2003.

  55. Comprehensive modernization of SYDEL v. 5 monitoring and energy balancing system in ZEC Bytom S.A heat and power plant, QKD controllers. Realized in 2004.

  56. Development of SYDEL r visualization, registering and energy balancing system in MEGAWAT Knurów. Realized in 2004.

  57. Development of SYDEL system in Fenice (FIAT Auto Poland SA Tychy) including metering of compressed air system. Realized in 2004.

  58. Construction, installation and go-live of SYDEL v. 5 system in Institute of Power Systems and Control laboratory at Silesian University of Technology. ELBIT controller. Realized in 2001-2004.

  59. Hardware and software installation for a new energy control module (SYDEL v. 5) in Góra¿d¿e Cement SA. Realized in 2004.

  60. SYDEL v. 5 system for energy monitoring for Górno¶l±skie Przedsiêbiorstwo Wodoci±gów (GPW), Paprocany pumping station. LZM meters, ELBIT concentrator. Realized in 2004.

  61. Inclusion of compressed air metering unit into SYDEL system in Fenice, FIAT Auto Poland Tychy. Realized in 2004.

  62. Control and visualization system for Przepompownia ¦cieków Rybarzowice pump station. SIMATIC S7-300 controller. Realized in 2004.

  63. Hardware and software installation for digital simulator of 200 MW power blocks, Warsaw University of Technology, Faculty of Electrical Engineering. Realized in 2004.

  64. NUMER. System modernization (upgrading to SYDEL v. 5) and development including two new stations and minimal power control in local gas power plant for KWK Budryk coal mine. QKD Elbit controllers. Realized in 2004.

  65. System modernization (upgrading to SYDEL v. 5, hardware upgrade), and development including two new system stations in Góra¿d¿e Cement, B&R controllers. Realized 2004/2005.

  66. SYDEL system development (new station by Elektrobudowa, 42 digital protection units MultiMUZ, ELBIT concentrator, additional signals) and upgrade into SYDEL v. 5, KWK Ziemowit coal mine. Realized in 2004/2005.

  67. System development for power set control, visualization and registering in CMC Zawiercie (Zawiercie foundry/ former Elserw) including a new 6 kV switchboard. Modicom Premium controllers, SYDEL v. 5 system. Realized in 2004.

  68. SYDEL system development including compressed air metering, Fenice, FIAT Auto Poland, Tychy. Realized in 2004.

  69. Instrumentation and automated dispatch and control and visualization system in a new gas boiler house in Koksownia Przyja¼ñ coke works. FANUC 90-30 controller, INTOUCH visualization system. Realziation in 2004/2005.

  70. SYDEL v. 5 system for energy consumption control, balancing and forecasting and supervision of energy system in SGL Carbon Racibórz. Modicon Premium controllers. Realized in 2005.

  71. SYDEL v. 5 system for control and visualization of heating system in KWK Jankowice coal mine shaft. Realized in 2005.

  72. SYDEL v. 5 system for visualization and signaling of electric parameters in WP-70 signal cabin in PEC Gliwice, ELBIT controller, SINOPTIC synoptic board. Realized in 2005.

  73. Sydel v. 5 system for visualization and control for wastewater station Halemba Centrum. B&R controllers. SINOPTIC synoptic board. Realized in 2006.

  74. Modernization of hardware and software structure of visualization and balancing modules in SYDEL v. 5 system. Fenice Poland FIAT Auto Poland, Tychy. ELBIT concentrators and controllers. Realized in 2005/2006.

  75. SYDEL system development including energy balancing function, energy reports and electro-energetic set parameters miming. ELBIT controllers and concentrators. Investor: PEC Gliwice. Realized in 2006.

  76. SYDEL system development for Fenice, FIAT Auto-Poland, Tychy including a new VoestAlpine switchboard. ELBIT controller. Investor: Elektromonta¿ no. 2, Katowice. Realized in 2006.

  77. SYDEL system upgrade into version 5.5 in Megawat Z-2, Knurów. Realized in 2006.

  78. Integration of existing monitoring and control systems (SYDEL, ASIX) in Megawat Knurów. SYDEL v. 5.5 superior system with energy media balancing and accounting. Realized in 2006.

  79. Modernization of accounting system in Zak³ady Koksownicze ?Zdzieszowice? coke works. Beckhoff controller, SYDEL v. 5.5 system. Realized in 2006.

  80. SYDEL v. 5.5 system for monitoring and balancing of energy media (electric energy, gas, heat) for Fenice Poland SA, Rzeszów. Realized in 2006/2007.

  81. System for control and visualizing in wastewater plants £êg i Spyrkówka for SEWiK Tatrzañska Komunalna Grupa Kapita³owa in Zakopane. Bernecker&Rainer controllers, iFIX 4.0 system.Realized in 2006/2007.

  82. SYDEL system upgrade into version 5.5 in Koksownia ?Przyja¼ñ? SA. System development. Realized in 2007.

  83. SYDEL system development for Fenice, FIAT Auto Poland, Tychy related to the enterprise enlargement. Realized in 2007.

  84. Modernization of SYDEL system into version 5.5 for ArcelorMittal Poland SA, D±browa Górnicza. Bernecker&Rainer controllers. Realized in 2008.

  85. Incorporation to the SYDEL system the visualization of a sag filter for PE Megawat, Bernecker&Rainer controller, PVI, OPC server. Realized in 2008.

  86. SYDEL system development for FENICE Polans, Tychy. Realized in 2008.

  87. SYDEL system development for Koksownia ?Przyja¼ñ? coke works. Realized in 2008.

  88. Projects and electric installations for deduster of BJ Industrie furnace for Zak³ad Hutniczy ?Orze³ Bia³y? in Piekary ¦l±skie. Realized in 2008.

  89. SYDEL 6.0 ?Energia? system for energy accounting for Zak³ady Azotowe ?Kêdzierzyn?. Cooperation with ASKOM Gliwice (ASIX ? metering and accounting system). Realized in 2008.

  90. SYDEL system for registering and visualization for Ciep³ownia ?Skoczów? (Ciep³ownictwo S³upiec sp. z o.o.) heat generating plant. Realized in 2008.

  91. SYDEL system for registering and visualization for Ciep³ownia ?Nowa Ruda? (Ciep³ownictwo S³upiec sp. z o.o.) heat generating plant. Realized in 2008.

  92. Instrumentation and automated heating control system in a shaft at KWK Bogdanka coal mine. B&R, iFIC controller. Realized in 2008.

  93. Development of the control system in £êg and Spyrówka wastewater plants for SEWiK. Zakopane. Sofrel-Lacroix controller. Realized in 2008.

  94. Realization of automatics system for pressure reduction and metering chamber, RPWiK Tychy. Sofrel-Lacroix. Controller. Realized in 2009.

  95. Automatic control system in Stacja Uzdatniania Wody Zwyciêczyca (Rzeszów) water treatment plant. Simatic controllers. Realized in 2009.

  96. SYDEL system for monitoring and balancing energy produced in a CHP for Koksownia ?Przyja¼ñ? S.A. coke works. Realized in 2008-2009.

  97. Development of SYDEL system for Fenice Poland (JO Rzeszów). Realized in 2009.

  98. Development of control and visualization system for wastewater plant Grodków. Realized in 2009.

  99. SYDEL system for monitoring and registering of rectifier unit parameters in ZACHEM Bydgoszcz. Realized in 2009.

  100. Development of control and visualization system in Ciep³ownia Skoczów heat plant. Realized in 2010.

  101. Development of control and visualization system in Ciep³ownia Nowa Ruda heat plant. Realized in 2010.

  102. Development of SYDEL system for monitoring and registering of rectifier unit parameters in ZACHEM Bydgoszcz. Beckhoff controllers. Realized in 2010.

  103. Concept for energy carriers balancing in Elektrociep³ownia EC Nowa combined heat and power plant in D±browa Górnicza. Realized in 2010.

  104. Development of SYDEL energy monitoring and managing system in FIAT Auto Poland (Fenice Poland). Realized in 2010.

  105. Development of SYDEL energy monitoring and managing system in Koksownia ?Przyja¼ñ? coke works, battery no 2. Realized in 2010.

  106. Hardware and software modernization for SYDEL and ASIX control and monitoring systems in PE Megawat, Knurów. Realized in 2010.

  107. SYDEL monitoring and control system for electrical power switchboard RMW in KWK Boles³aw ¦mia³y coal mine. Beckhoff controllers. Ordering Party: Elektromonta¿ Energetyka Wroc³aw. Realized in 2010.

  108. Hardware and software modernization for SYDEL monitoring and control system in general auxiliary switchboard in power plant Jaworzno III power plant II. Realized in 2010.

  109. Inserting data from modernized energy accounting system to the SYDEL system in Arecelor Mittal, D±browa Górnicza. Realized in 2010.